India’s first indigenous aircraft carrier, INS Vikrant, will be undocked on completion of structural work at the Cochin Shipyard on May 28.
“All
major equipment has gone into the vessel, which has now acquired the
shape of an aircraft carrier, with a finished hull. Barring a bit of
ongoing work on the super structure, structural work is all over and the
internal compartments have all been welded in,” said a yard official.
Outfitting
is steadily progressing at the moment, but a major part of it —
including piping, electrical cabling, control system wiring — will be
carried out after the vessel is launched, marking the culmination of the
third stage of work in the second phase of carrier construction for
which a contract was signed between Cochin Shipyard and the Navy in
December last year.
The extended first phase of work
on the carrier was completed in August 2013 when the carrier had its
official launch, but there was a delay in the Cabinet Committee on
Security (CCS) sanctioning money for the second phase, which as per a
schedule prepared in 2010 should be over in 2016.
The
CCS sanction for the first phase was Rs. 3,261 crore, while the
allocation for the critical second phase is Rs. 2,840 crore. The
equipment already fitted in will be set to work towards the end of the
ongoing phase after which basin trials will commence in 2017 to be on
time for delivery in end-2018. The aircraft carrier will displace over
40,000 tonnes at the time of its induction into the Navy.
While
some 14 contracts have been signed with the Russian Rosoboronexport for
the carrier’s aviation complex, delivery of major aviation equipment
has not begun yet.
The aviation complex is designed
by the Nevskoye Design Bureau, as Vikrant will have a complement of
Russian-origin MiG 29 K fighter planes operating from its flight deck
alongside the indigenously developed Naval LCA (when it receives
operational clearance).
Meanwhile, the yard is
awaiting clearances from the Directorate of Naval Design (DND) to start
installation of heating, ventilation and air conditioning systems.
“Ironically,
obsolescence of equipment already delivered and stacked for sometime
could pose a problem towards the end of the second phase when they are
set to work,” said an official.
Equipment such as the
massive gas turbines, for instance, would have outlived its guarantee
period by the time the pre-delivery trials begin, he pointed out.
thehindu
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.